Aspen Construction Company

  • Contact Person: Brad Baird
  • Contact Phone: 218-675-5808
  • Contact Email: brad@aspen-construction.com
  • Business Structure:
  • Corporate Entity (Not Tax Exempt)
  • Business Type:
  • Self Certified Small Disadvantaged Business
  • For Profit Organization
  • Industries Served: Construction Sand and Gravel Mining, Support Activities for Oil and Gas Operations, Support Activities for Coal Mining, Water Supply and Irrigation Systems, Sewage Treatment Facilities, Industrial Building Construction, Commercial and Institutional Building Construction, Water and Sewer Line and Related Structures Construction, Oil and Gas Pipeline and Related Structures Construction, Highway, Street, and Bridge Construction, Other Heavy and Civil Engineering Construction, Poured Concrete Foundation and Structure Contractors, Structural Steel and Precast Concrete Contractors, Masonry Contractors, Site Preparation Contractors, All Other Specialty Trade Contractors
  • Product Areas: ARCHITECT AND ENGINEERING- GENERAL: LANDSCAPING, INTERIOR LAYOUT, AND DESIGNING, A/E SVCS. (INCL LANDSCAPING INTERIO

Sampling of Federal Government Funding Actions/Set Asides

In order by amount of set aside monies.

  • $9,500 - Thursday the 3rd of January 2013
    Forest Service
    CHIPPEWA NATIONAL FOREST
    IGF::OT::IGF EQUIPMENT RENTAL WITH OPERATOR TO OPEN UP ROADS FOR EGRESS OF PUBLIC - DUE TO A SEVERE STORM CAUSING MANY ACRES DOWN AND TWISTED TREES.
  • $86,610 - Friday the 24th of August 2012
    Bureau Of Reclamation
    BILLINGS REGIONAL OFFICE
    CRITICAL FUNCTIONS - THIS ACTION IS A FUNDING ONLY ACTION TO RESERVE THE ESTIMATED FUNDING ANTICIPATED TO BE NECESSARY TO NEGOTIATE THE REQUEST FOR PROPOSAL #1 TO ADD ADDITIONAL RIPRAP TO THE SHADEHILL RESERVOIR STOCKPILE.
  • $6,782 - Wednesday the 14th of March 2012
    Department Of Army
    W7NG USPFO ACTIVITY MN ARNG
    SNOW PLOW VEE BLADE
  • $4,231 - Monday the 19th of March 2012
    Department Of Army
    W07V ENDIST ST PAUL
    LEECH LAKE WALKWAY
  • $40,538 - Monday the 3rd of December 2012
    Bureau Of Reclamation
    BILLINGS REGIONAL OFFICE
    CRITICAL FUNCTION - THIS ACTION RESERVES ESTIMATED CONTRACT FUNDING RELATED TO THE REQUEST FOR PROPOSAL FOR ANTICIPATED MODIFICATION TO THE CONTRACT REQUIREMENT. ADDITIONAL RIPRAP.
  • $366 - Monday the 3rd of December 2012
    Bureau Of Reclamation
    BILLINGS REGIONAL OFFICE
    CLOSELY ASSOCIATED - THIS MODIFICATION PROVIDES AN EQUITABLE ADJUSTMENT TO REPAIR THE BASE OF TRENTON DAM AS DIRECTED BY MODIFICATION 0002. THE MODIFICATION ALSO EXTENDS THE CONTRACT COMPLETION DATE TO NOVEMBER 4, 2011 AND PROVIDES ADDITIONAL FUNDS.
  • $3,128 - Wednesday the 22nd of August 2012
    Department Of Army
    W072 ENDIST NASHVILLE
    FUNDING (FEDERAL) FOR CLIN 0001
  • $31,143 - Thursday the 5th of April 2012
    Department Of Army
    W072 ENDIST NASHVILLE
    FUNDING (FEDERAL) FOR CLIN 0001
  • $29,655 - Tuesday the 21st of February 2012
    Department Of Army
    W071 ENDIST OMAHA
    CD - STREAMBANK PROTECTION, R00001, REVISE STONE GRADATION
  • $262,700 - Thursday the 29th of December 2011
    Department Of Army
    W071 ENDIST OMAHA
    C-OD-E PROJ #329437 STREAMBANK PROTECTION JAMESTOWN, ND SECTION 14

© Copyright 2019
The Collier Report
published by 1918 Media LLC.
Information displayed in this dossier has been provided through available open source or public sources. No reliance should be made by readers or Collier Report subscribers. Funding actions are complicated and do not always represent dollar-for-dollar payments to vendors nor do they represent payments in certain instances. Requests for the modification of displayed information may be made to help.desk@1918.media.