  • $551,707 - Wednesday the 9th of May 2012
    Department Of Army
    W072 ENDIST PITTSBURGH
    GEOTECHNICAL DRILLING AND INSTRUMENTATINO INSTALLATION, EAST BRANCH DAM, WILCOX, PENNSYLVANIA
  • $51,639 - Wednesday the 28th of December 2011
    Department Of Army
    W072 ENDIST PITTSBURGH
    GEOTECHNICAL DRILLING AND SITE INVESTIGATION, EAST BRANCH DAM, WILCOX, PA
  • $49,134 - Wednesday the 21st of December 2011
    Department Of Army
    W072 ENDIST PITTSBURGH
    CHARLEROI EMPTYING BASIN PLANS&SPECIFICATIONS
  • $46,897 - Wednesday the 16th of November 2011
    Department Of Army
    W072 ENDIST PITTSBURGH
    GEOTECHNICAL DRILLING AND SITE INVESTIGATION, EAST BRANCH DAM, WILCOX, PA
  • $463,592 - Wednesday the 12th of September 2012
    Department Of Army
    W072 ENDIST PITTSBURGH
    VIBRATING WIRE PRESSURE TRANSDUCER AND DATALOGGER INSTALLATION, EAST BRANCH DAM, WILCOX, PA
  • $25,000 - Monday the 14th of May 2012
    Department Of Army
    W072 ENDIST PITTSBURGH
    TAS::96 3134::TAS ARRA::YES::ARRA RECOVERYPROJECT#::10286::RP# SUPPORT DURING CONSTRUCTION OF THE CHARLEROI LOCKS&DAM, RIVER WALL.
  • $1,952 - Wednesday the 8th of August 2012
    Department Of Army
    W072 ENDIST PITTSBURGH
    RECOVERYPROJECT#10286#::RP#CHARLEROI LOCKS SUPPORT DURING CONSTRUCTION OF THE LOWER GUARD WALL. A&E SUPPORT, CHARLEROI, ALLEGHENY COUNTY, PA
  • $15,000 - Wednesday the 29th of February 2012
    Department Of Army
    W072 ENDIST PITTSBURGH
    CHARLEROI LOCKS - RIVER CHAMBER FILLING SYSTEM&MIDDLE WALL - SUPPORT DURING CONTRACT DEVELOPMENT
  • $138,882 - Tuesday the 28th of February 2012
    Department Of Army
    W072 ENDIST PITTSBURGH
    GEOTECHNICAL DRILLING AND SITE INVESTIGATION, EAST BRANCH DAM, WILCOX, PA
  • $117,291 - Tuesday the 28th of August 2012
    Department Of Army
    W072 ENDIST PITTSBURGH
    SERVICES FOR OPTION YEAR 1

© Copyright 2019
The Collier Report
published by 1918 Media LLC.
Information displayed in this dossier has been provided through available open source or public sources. No reliance should be made by readers or Collier Report subscribers. Funding actions are complicated and do not always represent dollar-for-dollar payments to vendors nor do they represent payments in certain instances. Requests for the modification of displayed information may be made to help.desk@1918.media.