  • $8,922 - Friday the 16th of September 2016
    Office Of Job Corps
    DEPT OF LABOR/EMPLOY AND TRAINING ADMIN
    MOD 0012 - RFC #29 FOR CONCRETE-ENCASED DUCT-BANK BELOW VOCATIONAL COMPLEX COURTYARD = $2,997.50; ADD TWO (2) CALENDAR CAYS TO THE PERIOD OF PERFORMANCE.
  • $66,617 - Friday the 16th of September 2016
    Employment And Training Administration
    DEPT OF LABOR/EMPLOY AND TRAINING ADMIN
    MOD 0012 - RFC #29 FOR CONCRETE-ENCASED DUCT-BANK BELOW VOCATIONAL COMPLEX COURTYARD = $2,997.50; ADD TWO (2) CALENDAR CAYS TO THE PERIOD OF PERFORMANCE.
  • $534,000 - Friday the 16th of September 2016
    Employment And Training Administration
    DEPT OF LABOR/EMPLOY AND TRAINING ADMIN
    MOD 0009 - RFC #38 TO STABALIZE THE SLOPE COLLAPSE FOR SE SIDE OF SITE = $300,000.00; ADD ADDITIONAL 15 CALENDAR DAYS. NEGOTIATIONS ARE STILL ONGOING SINCE ESTIMATED COSTS TO STABILIZE SLOPE(S) REMAIN UNDETERMINED BY THE GENERAL CONTRACTOR (GC)&THE GOVERNMENT.
  • $43,361 - Friday the 16th of September 2016
    Employment And Training Administration
    DEPT OF LABOR/EMPLOY AND TRAINING ADMIN
    MOD 0012 - RFC #29 FOR CONCRETE-ENCASED DUCT-BANK BELOW VOCATIONAL COMPLEX COURTYARD = $2,997.50; ADD TWO (2) CALENDAR CAYS TO THE PERIOD OF PERFORMANCE.
  • $319,267 - Friday the 16th of September 2016
    Employment And Training Administration
    DEPT OF LABOR/EMPLOY AND TRAINING ADMIN
    MOD 0012 - RFC #29 FOR CONCRETE-ENCASED DUCT-BANK BELOW VOCATIONAL COMPLEX COURTYARD = $2,997.50; ADD TWO (2) CALENDAR CAYS TO THE PERIOD OF PERFORMANCE.
  • $300,000 - Friday the 16th of September 2016
    Employment And Training Administration
    DEPT OF LABOR/EMPLOY AND TRAINING ADMIN
    MOD 0009 - RFC #38 TO STABALIZE THE SLOPE COLLAPSE FOR SE SIDE OF SITE = $300,000.00; ADD ADDITIONAL 15 CALENDAR DAYS. NEGOTIATIONS ARE STILL ONGOING SINCE ESTIMATED COSTS TO STABILIZE SLOPE(S) REMAIN UNDETERMINED BY THE GENERAL CONTRACTOR (GC)&THE GOVERNMENT.
  • $300,000 - Friday the 16th of September 2016
    Employment And Training Administration
    DEPT OF LABOR/EMPLOY AND TRAINING ADMIN
    MOD 0012 - RFC #29 FOR CONCRETE-ENCASED DUCT-BANK BELOW VOCATIONAL COMPLEX COURTYARD = $2,997.50; ADD TWO (2) CALENDAR CAYS TO THE PERIOD OF PERFORMANCE.
  • $2,998 - Friday the 16th of September 2016
    Employment And Training Administration
    DEPT OF LABOR/EMPLOY AND TRAINING ADMIN
    MOD 0012 - RFC #29 FOR CONCRETE-ENCASED DUCT-BANK BELOW VOCATIONAL COMPLEX COURTYARD = $2,997.50; ADD TWO (2) CALENDAR CAYS TO THE PERIOD OF PERFORMANCE.
  • $294,969 - Friday the 16th of September 2016
    Employment And Training Administration
    DEPT OF LABOR/EMPLOY AND TRAINING ADMIN
    MOD 0012 - RFC #29 FOR CONCRETE-ENCASED DUCT-BANK BELOW VOCATIONAL COMPLEX COURTYARD = $2,997.50; ADD TWO (2) CALENDAR CAYS TO THE PERIOD OF PERFORMANCE.
  • $26,218 - Friday the 16th of September 2016
    Employment And Training Administration
    DEPT OF LABOR/EMPLOY AND TRAINING ADMIN
    MOD 0012 - RFC #29 FOR CONCRETE-ENCASED DUCT-BANK BELOW VOCATIONAL COMPLEX COURTYARD = $2,997.50; ADD TWO (2) CALENDAR CAYS TO THE PERIOD OF PERFORMANCE.

© Copyright 2019
The Collier Report
published by 1918 Media LLC.
Information displayed in this dossier has been provided through available open source or public sources. No reliance should be made by readers or Collier Report subscribers. Funding actions are complicated and do not always represent dollar-for-dollar payments to vendors nor do they represent payments in certain instances. Requests for the modification of displayed information may be made to help.desk@1918.media.