The Collier Report of U.S. Government Contracting

Old School Reporting Using Modern Technology

Robles And Sons Inc as Robles Service Group

  • Robles And Sons Inc as Robles Service Group

  • View government funding actions
  • Cibolo, TX 781083614
  • Estimated Number of Employees: 110
  • Estimated Annual Receipts: $7,500,000

Sampling of Federal Government Funding Actions/Set Asides

In order by amount of set aside monies.

  • $9,600 - Friday the 3rd of August 2012
    Department Of Army
    W075 ENDIST ALBUQUERQUE
    D/B, RE-ROOF&HVAC UPGRADE, ICE EL PASO MODIFICATION FOR TEMP COOLING OF 6 DORMITORIES
  • $9,540 - Wednesday the 16th of May 2012
    Public Buildings Service
    GSA/PBS BORDER SECTION
    REPLACEMENT OF A 1 TON FAN COIL UNIT TO COOL A COMPUTER SERVER ROOM FOR THE US PUBLIC DEFENDER'S OFFICES LOCATED AT THE RCW FEDERAL BLDG. IN EL PASO, TX.
  • $85,682 - Friday the 18th of November 2011
    Department Of Air Force
    FA4460 19 CONS LGC
    ASBESTOS ABATEMENT B940
  • $8,538 - Thursday the 20th of September 2012
    Public Buildings Service
    GSA/PBS BORDER SECTION
    THIS ORDER IS TO PAINT THE LOBBY AT THE OLD COURT HOUSE IN EL PASO TX
  • $8,435 - Wednesday the 12th of September 2012
    Public Buildings Service
    GSA/PBS BORDER SECTION
    THE REMOVAL OF THE EXISTING VCT FLOORING AND VINYL BASE AND REPLACE WITH PREMIUM GRADE VCT FLOORING AND VINYL BASE AT THE PDN FAMILY DETENTION FACILITY IN EL PASO, TX.
  • $832 - Thursday the 10th of May 2012
    Public Buildings Service
    GSA/PBS BORDER SECTION
    PAINTING PRODUCT NOTATED IN THE ORIGINAL SOW WAS NOT THE BEST FIT FOR A HIGH HUMIDITY CLIMATE. THE CONTRACTOR HAD ALSO SUBMITTED FOR A PRODUCT THAT WAS A LOWER QUALITY REQUESTED IN THE SOW. AFTER NEGOTIATIONS, THERE WAS AN AGREEMENT TO SPLIT THE COST FOR THE PRODUCT THAT WOULD BEST FIT THE HUMIDITY CLIMATE.
  • $7,678 - Tuesday the 27th of March 2012
    Public Buildings Service
    GSA/PBS BORDER SECTION
    ADDING LINE ITEMS FOR ADDITIONAL WORK WITHIN THE PROJECT SOW FOR THE VISCOUNT RENOVATION PROJECT IN EL PASO, TX.
  • $7,329 - Tuesday the 22nd of November 2011
    Public Buildings Service
    GSA/PBS BORDER SECTION
    MOLD REMEDIATION AND BUILD BACK IN A PORTION OF A HALLWAY IN THE RC WHITE FEDERAL BUILDING, EL PASO, TX.
  • $69,222 - Friday the 3rd of August 2012
    Department Of Army
    W075 ENDIST ALBUQUERQUE
    D/B, RE-ROOF&HVAC UPGRADE, ICE EL PASO MODIFICATION FOR ELECTRICAL REVISIONS FOR RTU'S
  • $5,993 - Thursday the 19th of January 2012
    Public Buildings Service
    GSA/PBS BORDER SECTION
    REPLACE LIGHT POLE ON OUTBOUND LANES OF THE BOTA LPOE IN EL PASO, TX.

© Copyright 2019
The Collier Report
published by 1918 Media LLC.
Information displayed in this dossier has been provided through available open source or public sources. No reliance should be made by readers or Collier Report subscribers. Funding actions are complicated and do not always represent dollar-for-dollar payments to vendors nor do they represent payments in certain instances. Requests for the modification of displayed information may be made to help.desk@1918.media.