  • $8,445 - Wednesday the 4th of April 2012
    Department Of Army
    W072 ENDIST LOUISVILLE
    CONSTRUCTION OF ARC WINDER, GA
  • $8,413 - Thursday the 22nd of March 2012
    Department Of Army
    W072 ENDIST LOUISVILLE
    CONSTRUCTION OF ARC WINDER, GA
  • $7,917 - Tuesday the 27th of March 2012
    Department Of Army
    W072 ENDIST LOUISVILLE
    CASE 008 PROVIDE 3 EMBANKMENT EXPLORATORY HAND AUGER BORING SAMPLES AND ASSOCIATED ANALYSIS, REMOVE AND REPLACE TOP 4' OF UNSUITABLE SOIL FROM CREEKSIDE EMBANKMENT OF DETENTION POND, REPLACE WITH SUITABLE SOILS FROM ONSITE BORROW MATERIAL AND COMPACT; PROVIDE GEOTECHNICAL CONSULTANT FIELD OBSERVATION AND REPORTS, U.S. ARMY RESERVE TRAINING CENTER, WINDER, GA
  • $60,990 - Thursday the 26th of April 2012
    Department Of Army
    W072 ENDIST LOUISVILLE
    CASE 015-3 CHANGES TO CEMENT BOARD IN KITCHEN, PART 3 FINAL, U.S. ARMY RESERVE CENTER, WINDER, GA
  • $6,000 - Thursday the 16th of February 2012
    Department Of Army
    W072 ENDIST LOUISVILLE
    CASE 014-1 PERFORM MISCELLANEOUS ARCHITECTURAL, MECHANICAL, ELECTRICAL, PLUMBING, CIVIL AND STRUCTURAL REVISIONS MADE TO DESIGN BY DESIGNER OF RECORD, PART 1 NOTICE TO PROCEED, U.S. ARMY RESERVE CENTER, WINDER, GA
  • $40,354 - Thursday the 26th of April 2012
    Department Of Army
    W072 ENDIST LOUISVILLE
    CASE 018 MAKE CHANGES IN ACCORDANCE WITH DESIGNER OF RECORD CHANGES AND OMISSIONS TO INCLUDE MECHANICAL, ELECTRICAL, AND ARCHITECTURAL, U.S. ARMY RESERVE CENTER, WINDER, GA
  • $340,308 - Monday the 12th of December 2011
    Department Of Army
    W072 ENDIST LOUISVILLE
    CONSTRUCTION OF ARC WINDER, GA
  • $33,411 - Wednesday the 30th of November 2011
    Department Of Army
    W072 ENDIST LOUISVILLE
    CASE 007 IMPLEMENT CHANGES MADE BY DESIGNER OF RECORD INCLUDING TRENCH DRAIN BENEATH BRAISING PAN, STAINLESS STEEL COLUMN CORNER GUARDS, MODIFY REBAR REQUIREMENTS FOR LOBBY FOOTINGS, ADD METAL WALL PANEL SECTION COVER, CLARIFY DIMENSIONS OF SOFFITS AND WINDOWS AND LOCATION OF CORNER GUARDS, AND OTHER SPECIFIED CHANGES, U. S. ARMY RESERVE CENTER, WINDER, GA
  • $30,000 - Friday the 13th of April 2012
    Department Of Army
    W072 ENDIST LOUISVILLE
    CONSTRUCTION OF ARC WINDER, GA
  • $21,119 - Tuesday the 17th of April 2012
    Department Of Army
    W072 ENDIST LOUISVILLE
    CASE 011 ADD STRUCTURAL SUPPORT IN OMS ROOM 110; CASE 012 ADD FASCIA FRAMING IN MAIN LOBBY; CASE 013 ADD AIR BARRIER COMPONENTS TO CEMENT BOARD AND PROVIDE WEATHERSEALS FOR INTERIOR DOORS, U.S. ARMY RESERVE TRAINING CENTER, WINDER, GA

© Copyright 2019
The Collier Report
published by 1918 Media LLC.
Information displayed in this dossier has been provided through available open source or public sources. No reliance should be made by readers or Collier Report subscribers. Funding actions are complicated and do not always represent dollar-for-dollar payments to vendors nor do they represent payments in certain instances. Requests for the modification of displayed information may be made to help.desk@1918.media.